A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Aptitude
Time and Work
Difficulty: Easy
Choose an option
-
A12 days
-
B15 days
-
C16 days
-
D18 days
Answer
Correct Answer: 15 days
Explanation
### Concept & Periodic Assistance Cycles
When a primary worker is assisted periodically (e.g., every third day), calculate the total work produced over the complete period (the multi-day cycle) before repeating.
### Step-by-Step Solution
* **Determine Total Work and Efficiencies:**
* LCM of 20, 30, and 60 is 60. Let Total Work = 60 units.
* A's efficiency = $60 \div 20 = 3 \text{ units/day}$.
* B's efficiency = $60 \div 30 = 2 \text{ units/day}$.
* C's efficiency = $60 \div 60 = 1 \text{ unit/day}$.
* **Analyze the 3-Day Work Cycle:**
* A works continuously, but receives help from both B and C only on the third day.
* Day 1: A works alone = 3 units.
* Day 2: A works alone = 3 units.
* Day 3: A, B, and C work together = $3 + 2 + 1 = 6 \text{ units}$.
* Total work done in one 3-day cycle = $3 + 3 + 6 = 12 \text{ units}$.
* **Calculate Number of Cycles:**
* Total work needed = 60 units.
* Number of 3-day cycles required = $60 \div 12 = 5 \text{ cycles}$.
* **Determine Total Time:**
* Total days = $5 \text{ cycles} \times 3 \text{ days/cycle} = 15 \text{ days}$.
### Exam Strategy & Shortcut
Find efficiencies: A=3, B=2, C=1 based on LCM=60. Every 3 days, the work produced is $A + A + (A+B+C) \rightarrow 3 + 3 + 6 = 12$ units. Total work $60 \div 12 = 5$ cycles. $5 \times 3 \text{ days} = 15 \text{ days}$.
### Common Pitfall
A frequent error is assuming B and C alternate their assistance on the third day, rather than assisting together. "assisted by B and C" implies both join simultaneously on that specific day.
### Final Answer
Therefore, the correct answer is **15 days**.