Difficulty: Medium
Correct Answer: 12 days
Explanation:
Introduction / Context:
Use the given joint time and B’s solo time to isolate A’s solo rate. Then, after the initial joint period, compute the remaining work and the time A needs to finish it alone.
Given Data / Assumptions:
Concept / Approach:
Compute work done in the first 4 days and then divide the remainder by A’s rate.
Step-by-Step Solution:
Work in first 4 days = 4 * (1/8) = 1/2.Remaining work = 1 − 1/2 = 1/2.A alone rate = 1/24 ⇒ time = (1/2) / (1/24) = 12 days.
Verification / Alternative check:
Check quickly: A would do the whole work in 24 days; finishing half takes 12 days.
Why Other Options Are Wrong:
10, 11, 13, 14 days mismatch the exact remaining half and A’s 1/24 per-day rate.
Common Pitfalls:
Using B’s 12-day time incorrectly or assuming 8 − 4 = 4 days naïvely.
Final Answer:
12 days
Discussion & Comments