Difficulty: Medium
Correct Answer: 0.5 mm
Explanation:
Introduction / Context:
“Twist” is the rate of change of cross-level (difference in elevation between the two rails) per unit length along the track. Excessive twist is a safety hazard and is tightly controlled in track standards. This problem practices converting absolute rail levels into cross-levels and then into twist per metre.
Given Data / Assumptions:
Concept / Approach:
Cross-level at a point = elevation of one rail minus the other. Twist = (cross-level at B − cross-level at A) / distance. Convert the difference into millimetres and divide by metres to obtain mm/m. Careful, consistent rail identification ensures correct sign; magnitude is usually reported for maintenance limits.
Step-by-Step Solution:
Verification / Alternative check (if short method exists):
Compute individual rail gradients and re-derive cross-levels to confirm; results will be identical. A quick reasonableness check: a 50 mm change over 100 m is small and within typical track tolerances for gradual twist.
Why Other Options Are Wrong:
0.4, 0.7, 0.8, and 1.0 mm/m do not match the exact arithmetic from the given levels and spacing. Only 0.5 mm/m equals 50 mm over 100 m.
Common Pitfalls (misconceptions, mistakes):
Mixing up which rail is higher; using average levels instead of cross-level; forgetting to convert metres to millimetres; dividing by 100 cm instead of 100 m.
Final Answer:
0.5 mm
Discussion & Comments