Work measurement: “Standard time” for an operation is defined as which of the following?

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    Normal time minus allowances
  • B
    Normal time plus allowances
  • C
    Representative (average observed) time multiplied by rating factor
  • D
    The observed time from a single fastest cycle
  • E
    Only the allowance time without observed work

Answer

Correct Answer: Normal time plus allowances

Explanation

Introduction / Context:Accurate standards underpin planning, costing, and incentive schemes. The relationship among observed time, normal time, and standard time must be clear to avoid under- or over-estimating capacity.

Given Data / Assumptions:

  • Observed times taken over several cycles.
  • Performance rating system to convert to normal time.
  • Allowances for fatigue, personal needs, and delays.

Concept / Approach:Representative (average) observed time * rating factor = normal time. Then, standard time = normal time + allowances. This ensures the standard reflects both expected performance and legitimate interruptions.

Step-by-Step Solution:

Compute average observed time.Apply rating: normal time = representative time * rating factor.Add allowances: standard time = normal time + allowances.

Verification / Alternative check:Classic work measurement texts define standard time exactly as normal time plus allowances.

Why Other Options Are Wrong:(a) Subtracting allowances is incorrect.(c) Describes normal time, not standard time.(d) A single fastest cycle is not representative.(e) Allowances alone are meaningless without normal time.

Common Pitfalls:Using too few observations; misrating performance; misapplying allowances.

Final Answer:

Normal time plus allowances