Difficulty: Easy
Correct Answer: All of the above
Explanation:
Introduction / Context:
Sewer design includes an allowance above the calculated full-flow area. This reserve capacity addresses uncertainties that can arise over the service life of the asset and reduces the risk of surcharge and overflows.
Given Data / Assumptions:
Concept / Approach:
Because sewers are capital-intensive and difficult to upsize, modest headroom in capacity is economical insurance. It helps absorb peak wet-weather inflows, unplanned connections, and modeling uncertainties without immediate upgrades.
Step-by-Step Solution:
1) Identify risk sources: infiltration/inflow during storms, demographic growth, misestimation of peaking factors.2) Recognize that a 25%–33% vacant area at design peak gives hydraulic margin before full-flow and surcharge.3) Conclude that all listed reasons justify the allowance.
Verification / Alternative check:
Utility standards often embed safety factors or residual capacity targets in new sewer design, confirming the multi-factor rationale.
Why Other Options Are Wrong:
Options A–C individually cover valid reasons, but the practice is motivated by all of them together.Option E: Reducing energy losses is not the primary justification for vacant area.
Common Pitfalls:
Final Answer:
All of the above