Difficulty: Medium
Correct Answer: All the above
Explanation:
Introduction / Context:Formwork striking and removal of props must balance safety and construction speed. Removing props too early can cause excessive deflection or cracking; too late delays cycle times and increases cost.
Given Data / Assumptions:
Concept / Approach:
Codes provide minimum periods for removal of props based on member type and span. Beams require longer support due to higher flexural stiffness demands and slower stiffness gain compared to slabs.
Step-by-Step Solution:
1) For slabs up to 4.5 m, typical prop removal time is 7 days.2) For slabs over 4.5 m, increase to about 14 days.3) For beams up to 6 m, about 14 days are required.4) For beams over 6 m, extend to around 21 days.Verification / Alternative check:
Project specifications may modify times based on cement type, admixtures, or accelerated curing. However, the listed figures represent widely taught baseline values.
Why Other Options Are Wrong:
Common Pitfalls:
Ignoring temperature effects and high early strength cements, which can shorten times, or cold weather that requires longer durations.
Final Answer:
All the above