Difficulty: Easy
Correct Answer: Greatest value of the above
Explanation:
Introduction / Context:Adequate spacing between reinforcing bars ensures proper aggregate flow, minimizes honeycombing, and allows compaction around bars. Codes prescribe a minimum clear spacing that depends on bar size and aggregate size.
Given Data / Assumptions:
Concept / Approach:
The minimum clear spacing should prevent aggregate blocking and allow adequate grout to surround bars. Hence, spacing is tied to bar diameter and aggregate size, and the controlling rule is to adopt the greatest of specified checks.
Step-by-Step Solution:
1) If bars are equal in diameter, one check equals that diameter.2) If bars are unequal, use the larger bar diameter as another check.3) A separate check is 5 mm more than the nominal maximum aggregate size.4) Adopt the greatest of these values to guarantee placement quality.Verification / Alternative check:
Concrete placement trials consistently show that respecting the largest controlling spacing delivers fewer voids and better consolidation around reinforcement.
Why Other Options Are Wrong:
Common Pitfalls:
Using bar diameter alone and ignoring aggregate size, which can cause blocking and honeycombing in congested regions.
Final Answer:
Greatest value of the above