  • 1. The organizational form in which the project manager has informal authority over team members and little or no input to team member?s performance appraisal is called

  • Options
  • A. weak matrix.
  • B. functional.
  • C. strong matrix.
  • D. composite.
  • Discuss
  • 2. A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

  • Options
  • A. Project integration plan.
  • B. WBS development plan.
  • C. Configuration management plan.
  • D. Scope management plan.
  • Discuss
  • 3. Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction phase of a project. you are currently in the process of activity sequencing. This is a example of what?

  • Options
  • A. Gatekeeping
  • B. Milestone
  • C. New scope for the project
  • D. Project integration
  • Discuss
  • 4. Decomposing tasks into smaller activities can be helpful in reducing the amount of stress associated with overwhelmingly large milestones. What is a feature of the hierarchical nature of the WBS?

  • Options
  • A. A WBS hierarchy prevents duplication
  • B. A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience.
  • C. The decomposition of tasks provides a detailed planning tool
  • D. The depth of a WBS is restricted to three levels, which avoids overplanning
  • Discuss
  • 5. The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?

  • Options
  • A. Change control system
  • B. Process analysis
  • C. Benchmarking
  • D. Configuration management system
  • Discuss
  • 6. Sensitivity analysis is used to

  • Options
  • A. identify the risks which have the largest potential impact on the project.
  • B. determine which risks are most troubling to the customer.
  • C. identify hidden requirements that were not recognized at the outset of the project.
  • D. determine which requirements will add the greatest customer satisfaction for the least effort.
  • Discuss
  • 7. Project Integration Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Monitor and Control Project Work phase?
  • Discuss
  • 8. Ambiguous jurisdiction is more common in a functional or weak matrix organization than a strong matrix or projectized organization. Why?

  • Options
  • A. Projectized organizations tend to be large in size
  • B. Conflict between a functional manager and a project manager is more common in a functional or weak matrix
  • C. Legal issues are more frequent in a functional or weak matrix organization
  • D. Projectized and strong matrix organizations are the best companies for a project manager to work for due to less ambiguity in scope development.
  • Discuss
  • 9. Integration is primarily concerned with

  • Options
  • A. ensuring that the time, scope and cost baselines are consistent with an acceptable quality standard and with the customer?s expectations.
  • B. getting people working together effectively toward common project goals through appropriate training, management and leadership.
  • C. effectively integrating the processes among the project management process groups that are required to accomplish project objectives with an organization?s defined procedures.
  • D. ensuring that all the tools and techniques of the various planning processes are appropriately scaled to the complexity and risk exposure of the project.
  • Discuss
  • 10. Which of the following is usually not considered a goal of portfolio management?

  • Options
  • A. To manage the effective and efficient use of resources.
  • B. To balance the portfolio among incremental and radical investments.
  • C. To maximize the value of the portfolio by careful examination of candidate projects and exclusion of those no meeting strategic objectives.
  • D. To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.
  • Discuss