Network scheduling terminology (PERT/CPM): The start or completion of a task (with no duration itself) is called a(n) ________.

Difficulty: Easy

Correct Answer: Event

Explanation:


Introduction / Context:
PERT/CPM models represent projects as networks of activities and events. Correct terminology is essential for reading and building these networks.



Given Data / Assumptions:

  • Activities consume time and possibly resources.
  • Events (nodes) mark the start or finish of activities and have zero duration.
  • Precedence relationships connect events via activities.


Concept / Approach:
In activity-on-arrow (AOA) or activity-on-node (AON) representations, the notion of a milestone (event) captures the instant a state is achieved (e.g., “foundation complete”). It has no time span; activities carry duration.



Step-by-Step Solution:

Identify whether the item consumes time → if yes, it is an activity.If it is an instantaneous marker of start/finish with zero duration → it is an event.Therefore, “start or completion of task” is an event.


Verification / Alternative check:
Network definitions: nodes/milestones/events have zero duration; arcs/activities have positive duration.



Why Other Options Are Wrong:
(b) Activity always has duration; (c) duration is a quantitative attribute, not an object; (d) contradicts standard definitions.



Common Pitfalls:
Using “activity” and “event” interchangeably; assigning duration to events.



Final Answer:

Event

More Questions from Industrial Engineering and Production Management

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion