Difficulty: Easy
Correct Answer: Event
Explanation:
Introduction / Context:
PERT/CPM models represent projects as networks of activities and events. Correct terminology is essential for reading and building these networks.
Given Data / Assumptions:
Concept / Approach:
In activity-on-arrow (AOA) or activity-on-node (AON) representations, the notion of a milestone (event) captures the instant a state is achieved (e.g., “foundation complete”). It has no time span; activities carry duration.
Step-by-Step Solution:
Verification / Alternative check:
Network definitions: nodes/milestones/events have zero duration; arcs/activities have positive duration.
Why Other Options Are Wrong:
(b) Activity always has duration; (c) duration is a quantitative attribute, not an object; (d) contradicts standard definitions.
Common Pitfalls:
Using “activity” and “event” interchangeably; assigning duration to events.
Final Answer:
Event
Discussion & Comments