P.M.T.S. (Predetermined Motion Time Systems) include
M.T.M. (Method Time Measurement)
W.F.S. (Work Factor Systems)
B.M.T.S. (Basic Motion Time Study)
all of these
Correct Answer:
all of these
← Previous Question
Next Question→
More Questions from
Industrial Engineering and Production Management
Work study is mainly aimed at
Break even analysis represents the relationship between cost and volume.
According to Muther, the basic principle of best layout is
If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be
Product layout is used for
Product layout is also known as
In fixed position layout
The time taken by a trained worker to perform an operation, while working a steady pace, is known as
In product layout
Normal time is the ratio of representative time to the rating factor.
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments