Home » Mechanical Engineering » Industrial Engineering and Production Management

PERT expected time (probabilistic): compute using optimistic, most likely, pessimistic For an activity with three time estimates: tₒ (optimistic), tₙ (most likely), and tₚ (pessimistic). Choose the correct expression for the PERT expected time.

Difficulty: Medium

Correct Answer: (tₒ + 4 tₙ + tₚ) / 6

Explanation:


Approach (Beta distribution assumption)
PERT models activity time with a (shifted) beta distribution and uses a weighted mean favouring the most likely time.


Expected time formula
te = (tₒ + 4 tₙ + tₚ) / 6


Illustration
If tₒ = 4, tₙ = 6, tₚ = 10 (days):te = (4 + 4×6 + 10)/6 = (4 + 24 + 10)/6 = 38/6 ≈ 6.33 days.


Common pitfalls
Do not average equally; PERT gives 4× weight to the most likely estimate.


Final Answer
(tₒ + 4 tₙ + tₚ) / 6.

← Previous Question Next Question→

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion