Difficulty: Medium
Correct Answer: (tₒ + 4 tₙ + tₚ) / 6
Explanation:
Approach (Beta distribution assumption)
PERT models activity time with a (shifted) beta distribution and uses a weighted mean favouring the most likely time.
Expected time formula
te = (tₒ + 4 tₙ + tₚ) / 6
Illustration
If tₒ = 4, tₙ = 6, tₚ = 10 (days):te = (4 + 4×6 + 10)/6 = (4 + 24 + 10)/6 = 38/6 ≈ 6.33 days.
Common pitfalls
Do not average equally; PERT gives 4× weight to the most likely estimate.
Final Answer
(tₒ + 4 tₙ + tₚ) / 6.