Difficulty: Easy
Correct Answer: triple time estimate
Explanation:
Concept
PERT models activity duration uncertainty with three estimates: optimistic (a), most likely (m), and pessimistic (b). These combine to give the expected time and variance for network analysis.
Why triple
Using three points better captures uncertainty than a single or double estimate, improving schedule risk analysis.
Final Answer
triple time estimate