Project management fundamentals: PERT as an event-oriented technique Consider the PERT (Programme Evaluation and Review Technique) network method used for scheduling under uncertainty. State whether PERT is event-oriented, as opposed to activity-oriented like CPM.

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    True — PERT is event-oriented (milestones focus)
  • B
    False — PERT is activity-oriented
  • C
    True only for deterministic networks
  • D
    False; PERT is only for time–cost tradeoff analysis

Answer

Correct Answer: True — PERT is event-oriented (milestones focus)

Explanation

ConceptPERT emphasizes events (milestones) and uses three-time estimates (optimistic, most likely, pessimistic) to handle uncertainty. CPM is typically activity-oriented and deterministic.

ConclusionTherefore, the statement “PERT is an event-oriented technique” is correct.

Final AnswerTrue — PERT is event-oriented (milestones focus).