Difficulty: Easy
Correct Answer: True — PERT is event-oriented (milestones focus)
Explanation:
Concept
PERT emphasizes events (milestones) and uses three-time estimates (optimistic, most likely, pessimistic) to handle uncertainty. CPM is typically activity-oriented and deterministic.
Conclusion
Therefore, the statement “PERT is an event-oriented technique” is correct.
Final Answer
True — PERT is event-oriented (milestones focus).