Difficulty: Easy
Correct Answer: All of these
Explanation:
Introduction / Context:
PERT excels in environments with uncertain task durations and complex interdependencies. It supports probabilistic scheduling and risk-informed decisions across diverse projects.
Given Data / Assumptions:
Concept / Approach:
By using three-time estimates for each activity, PERT calculates expected times and variances, then assesses the critical path and completion probabilities. This fits R&D, campaigns, and installations where uncertainty is high.
Step-by-Step Solution:
Verification / Alternative check:
Examples from R&D and marketing launches often use PERT to handle uncertainty and communicate schedule confidence.
Why Other Options Are Wrong:
Each single domain is valid; the inclusive answer acknowledges PERT’s cross-domain suitability under uncertainty.
Common Pitfalls:
Forgetting to update estimates as information improves; misidentifying dependencies.
Final Answer:
All of these