Network scheduling terminology (PERT/CPM): The start or completion of a task (with no duration itself) is called a(n) ________.

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    Event
  • B
    Activity
  • C
    Duration
  • D
    None of these

Answer

Correct Answer: Event

Explanation

Introduction / Context:PERT/CPM models represent projects as networks of activities and events. Correct terminology is essential for reading and building these networks.

Given Data / Assumptions:

  • Activities consume time and possibly resources.
  • Events (nodes) mark the start or finish of activities and have zero duration.
  • Precedence relationships connect events via activities.

Concept / Approach:In activity-on-arrow (AOA) or activity-on-node (AON) representations, the notion of a milestone (event) captures the instant a state is achieved (e.g., “foundation complete”). It has no time span; activities carry duration.

Step-by-Step Solution:

Identify whether the item consumes time → if yes, it is an activity.If it is an instantaneous marker of start/finish with zero duration → it is an event.Therefore, “start or completion of task” is an event.

Verification / Alternative check:Network definitions: nodes/milestones/events have zero duration; arcs/activities have positive duration.

Why Other Options Are Wrong:(b) Activity always has duration; (c) duration is a quantitative attribute, not an object; (d) contradicts standard definitions.

Common Pitfalls:Using “activity” and “event” interchangeably; assigning duration to events.

Final Answer:

Event