In a network shown in the below figure, the critical path is along
1-2-3-4-8-9
1-2-3-5-6-7-8-9
1-2-3-4-7-8-9
1-2-5-6-7-8-9
Correct Answer:
1-2-3-5-6-7-8-9
← Previous Question
Next Question→
More Questions from
Industrial Engineering and Production Management
Fixed position layout is also known as
PERT is an event oriented technique.
Line organisation is suitable for a big organisation.
Direct expenses include
Probabilistic time for completion of any activity can be found out from
A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called
Military type of organisation is known as
In value engineering, the term value refers to
A diagram showing the path followed by men and materials while performing a task is known as
If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments