Project planning tools: appropriate use of a bar chart (Gantt) Match the bar chart's capability and limitations to project size and complexity. Select the type of work where a bar chart is most suitable.

Difficulty: Easy

Correct Answer: Minor work (simple, few interdependencies)

Explanation:

Concept
Bar charts are straightforward and effective for simple/small projects but do not model complex precedence as well as CPM/PERT.


Why this choice
Minor work usually has limited activities and dependencies, matching the strengths of bar charts.


Final Answer
Minor work (simple, few interdependencies)