Time study calculations: role of the rating factor In time study, after observing cycles, what does multiplying by the performance rating (rating factor) determine? Choose the correct outcome.

Difficulty: Easy

Correct Answer: Normal time of a worker

Explanation:

Given/ConceptObserved Time × Rating Factor = Normal Time. Then Standard Time = Normal Time × (1 + Allowances).

Step-by-step1) Observe cycle times → average → representative time.2) Apply rating factor → normal time.3) Add allowances → standard time.

Final AnswerNormal time of a worker