Difficulty: Easy
Correct Answer: All of the above
Explanation:
Introduction / Context:
Concrete walls in buildings are frequently cast in lifts. Practical and structural considerations guide where horizontal construction joints are placed during staging.
Given Data / Assumptions:
Concept / Approach:
Horizontal joints align with architectural and structural lines that naturally interrupt the wall. These include floor levels (slab junctions), window sill levels (below openings), and soffit lines of beams or slabs. Choosing these makes formwork simpler, allows controlled shear transfer, and avoids random joints in highly stressed regions.
Step-by-Step Solution:
Identify typical horizontal planes → floors, sills, and soffits.Confirm that these planes suit staging and structural continuity.Therefore, all listed levels are acceptable in practice.
Verification / Alternative check:
Construction drawings commonly indicate pour lifts at sill and floor levels to coordinate rebar splices and embeds.
Why Other Options Are Wrong:
Picking a single level ignores other equally common and suitable joint planes.
Common Pitfalls:
Stopping pours at random elevations leading to rework; neglecting joint surface preparation prior to next lift.
Final Answer:
All of the above.