Difficulty: Medium
Correct Answer: d = 0.5 B
Explanation:
Introduction / Context:For roadside, storm-water, or small irrigation drains up to about 15 m³/s, designers often begin with empirical proportions before iterating with Manning or Chézy equations. A typical starting proportion is a depth roughly half the top width, providing a stable, maintainable section.
Given Data / Assumptions:
Concept / Approach:
Using a rule-of-thumb like d = 0.5 B (equivalently B ≈ 2 d) provides a reasonable hydraulic radius and side-slope economy for first sizing. The section is then refined to satisfy permissible velocities, freeboard, side slopes, and material constraints using Manning’s formula and stability checks.
Step-by-Step Solution:
Start with d = 0.5 B as a preliminary proportion.Select side slopes based on soil stability (e.g., 1V:1.5H).Apply Manning: Q = (1/n) * A * R^(2/3) * S^(1/2) and iterate B and d.Check velocity limits and provide freeboard; adjust as needed.Verification / Alternative check:
Sensitivity analysis against B/d ratios near 2 shows minor differences in area and hydraulic radius; final sizing is governed by Manning and stability criteria.
Why Other Options Are Wrong:
d = 0.2 B produces too shallow a section; B = 0.2 d and B = 0.5 d invert the proportion unrealistically, giving very narrow or very deep sections.
Common Pitfalls:
Keeping empirical proportions without hydraulic verification; ignoring freeboard; neglecting sediment transport and maintenance access.
Final Answer:
d = 0.5 B
Discussion & Comments