Building drainage pipe commissioning — pre-use checks: Before putting drainage pipes in buildings to service, which of the following tests are applied?

Difficulty: Easy

Correct Answer: All the above

Explanation:


Introduction / Context:
Plumbing and building drainage systems must be leak-tight, correctly aligned, and free from obstructions. Several standard tests are employed before commissioning to verify workmanship and system integrity.


Given Data / Assumptions:

  • Pipes, joints, and fittings have been installed as per layout.
  • Tests are conducted prior to covering or backfilling wherever applicable.
  • Building codes typically mandate more than one test.


Concept / Approach:

  • Water test: Confirms watertightness under hydrostatic head.
  • Smoke test: Detects leaks and improper traps by observing smoke escape.
  • Straightness test: Ensures alignment to minimize blockages and maintain gradient.
Combining these tests provides confidence in performance during actual use.


Step-by-Step Solution:
Identify the standard set of tests from codes and practice.All three tests are commonly required or recommended.Therefore, the correct response is “All the above.”


Verification / Alternative check:
Many municipal and national plumbing codes include water and smoke tests explicitly; straightness/alignment checks are standard site QA/QC procedures.


Why Other Options Are Wrong:
Selecting only one omits other equally necessary tests.“None of these” contradicts accepted practice.


Common Pitfalls:

  • Skipping smoke tests in favor of only water testing.
  • Ignoring alignment, which can lead to frequent choking.


Final Answer:
All the above

More Questions from Waste Water Engineering

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion