  • Question
  • Raghu can do a job in 12 days alone and Sam can do the same job in 15 days alone. A third person Aru whose efficiency is two-third of efficiency of both Ram and Shyam together, can do the same job in how many days alone?


  • Options
  • A. 10
  • B. 12
  • C. 13
  • D. 15

  • Correct Answer
  • 10 

    Explanation

    One day work of Raghu and Sam together = 1/12 + 1/15 = 9/60 = 3/20

    Aru efficiency = 2/3 of (Raghu + Sam)

    Number of days required for Aru to do thw work alone = 3/2 x 20/3 = 10 days. 

  • Tags: AIEEE, Bank Exams, CAT, GATE, Analyst, Bank Clerk, Bank PO

    Time and Work problems


    Search Results


    • 1. A mother can do a certain job in x hours. Her daughter takes twice as long to do the job. Working together, they can do the job in 6 hours. How many hours does the mother take to do the job ?

    • Options
    • A. 3
    • B. 6
    • C. 9
    • D. 12
    • Discuss
    • 2. A garrison of 2000 men has provisions for 54 days. At the end of 15 days, a reinforcement arrives, and it is now found that the provisions will last only for 20 days more. What is the reinforcement ?

    • Options
    • A. 1900
    • B. 2100
    • C. 1700
    • D. 2000
    • Discuss
    • 3. A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?

    • Options
    • A. 2 days
    • B. 3 days
    • C. 4 days
    • D. 5 days
    • Discuss
    • 4. Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?

    • Options
    • A. 3 days
    • B. 2 days
    • C. 6 days
    • D. 12 days
    • Discuss
    • 5. A woman fills a bucket in 6 minutes. 1845 buckets have to be filled from 8 am. to 9:30 am. How many woman employees should be employed for this task?

    • Options
    • A. 111
    • B. 117
    • C. 123
    • D. 139
    • Discuss
    • 6. A can finish a work in 15 days and B can do the same work in 12 days . B worked for 8 days and left the job .In how many days, A alone can finish the remaining work?

    • Options
    • A. 6 days
    • B. 5 days
    • C. 4 days
    • D. 3 days
    • Discuss
    • 7. In a public bathroom there are n taps 1,2,3...n. Tap1 and Tap2 take equal time to fill the tank while Tap3 takes half the time taken by Tap2 and Tap4 takes half the time taken by Tap3. Similarly each next number of tap takes half the time taken by previous number of Tap i.e, K-th Tap takes half the time taken by (K-1)th Tap. If the 10th tap takes 2 hours to fill the tank alone then what is the ratio of efficiency of 8th tap and 12th tap, respectively?

    • Options
    • A. 4:1
    • B. 5:3
    • C. 16:1
    • D. 1:16
    • Discuss
    • 8. Two persons Shyam and Rahim can do a job in 32 days together. Rahim can do the same job in 48 days alone. They started working together and after working 8 days Rahim is replaced by a third person Ram whose efficiency is half that of Rahim. Find in how many days the remaining work will be completed by both Shyam and Ram together?

    • Options
    • A. 16 days
    • B. 72/5 days
    • C. 15 days
    • D. 96/5 days
    • Discuss
    • 9. If a soldier fires 7 shots from a gun in 12 minutes then find the total number of shots fired by the man in 3/2 hrs.

    • Options
    • A. 45
    • B. 44
    • C. 46
    • D. 47
    • Discuss
    • 10. A certain job was assigned to a group of women to do it in 20 days. But 12 women did not turn up for the job and the remaining did the job in 32 days. The original number of women in the group was?

    • Options
    • A. 36
    • B. 32
    • C. 22
    • D. 28
    • Discuss