Difficulty: Hard
Correct Answer: 1/6
Explanation:
Introduction / Context:
This is an advanced time and work problem involving four workers A, B, C, and D and a parameter p. Different people work during different intervals, and a certain percentage of the work is left for D. We must first determine the value of p from the given conditions, then imagine a new scenario where C and D work together for p days and compute what fraction of the work will still remain.
Given Data / Assumptions:
Concept / Approach:
We first convert the individual times into daily work rates. The statement that D completes the remaining 5 / 12 of the work in 10 days allows us to compute D's rate. Since that remaining fraction is the part left after A, B, and C have worked during the first two phases, we know that A, B, and C together complete 7 / 12 of the work in total during those phases. Setting up an equation for this 7 / 12 in terms of p gives us the value of p. Then, in the hypothetical scenario where C and D work together for p days, we use their combined rate to compute the fraction of work completed, and subtract this from 1 to find what fraction remains.
Step-by-Step Solution:
Rates: A's rate = 1 / 72, B's rate = 1 / 48, C's rate = 1 / 36.
Let D's rate be d jobs per day.
Remaining work fraction = 125 / 3 percent = 5 / 12.
D completes 5 / 12 of the work in 10 days, so d * 10 = 5 / 12, hence d = (5 / 12) / 10 = 1 / 24.
Total work done by A, B, and C during the first two phases is 1 - 5 / 12 = 7 / 12.
Work in phase 1 (p/2 days by A and B) = (1 / 72 + 1 / 48) * (p / 2).
Compute A + B: 1 / 72 + 1 / 48 = (2 / 144 + 3 / 144) = 5 / 144.
So phase 1 work = (5 / 144) * (p / 2) = 5p / 288.
Work in phase 2 ((p + 6)/3 days by A, B, and C) = (1 / 72 + 1 / 48 + 1 / 36) * ((p + 6) / 3).
A + B + C = 1 / 72 + 1 / 48 + 1 / 36 = 1 / 16 (after simplifying).
So phase 2 work = (1 / 16) * ((p + 6) / 3) = (p + 6) / 48.
Total work by A, B, and C = 5p / 288 + (p + 6) / 48.
Set this equal to 7 / 12 and solve for p: 5p / 288 + (p + 6) / 48 = 7 / 12.
Converting to a common denominator and simplifying gives p = 12 days.
Now consider the hypothetical scenario: C and D work together for p days = 12 days.
C's rate = 1 / 36, D's rate = 1 / 24, so combined rate = 1 / 36 + 1 / 24 = (2 / 72 + 3 / 72) = 5 / 72 jobs per day.
In 12 days, work done by C and D = 12 * (5 / 72) = 60 / 72 = 5 / 6.
Remaining work fraction = 1 - 5 / 6 = 1 / 6 of the job.
Verification / Alternative check:
You can double check the computation of p by substituting p = 12 into the expressions for phase 1 and phase 2 work: phase 1 gives 5 * 12 / 288 = 60 / 288 = 5 / 24, while phase 2 gives (12 + 6) / 48 = 18 / 48 = 3 / 8. Adding 5 / 24 and 3 / 8 gives (5 / 24 + 9 / 24) = 14 / 24 = 7 / 12, confirming that 5 / 12 of the work is left for D. The second scenario with C and D also checks out as 5 / 6 completed and 1 / 6 remaining.
Why Other Options Are Wrong:
1/5, 1/7, and 1/8 would correspond to different values of p or different rates and do not match the carefully derived fraction.
1/9 is significantly smaller and would mean that C and D together complete a much larger fraction than they actually do according to their rates.
Common Pitfalls:
There are several places to go wrong: misreading 125/3 percent, forgetting that it represents 5 / 12 of the work; making algebraic mistakes when solving for p; or miscomputing the combined rates of A, B, C, and D. A clear step by step approach, careful fraction arithmetic, and checking intermediate results are essential for such multi stage problems.
Final Answer:
If C and D work together for p days, the fraction of work that will remain is 1/6 of the total.
Discussion & Comments