Let A's 1 day's work=x and B's 1 day's work=y
Then x+y = 1/40 and 20x+60y=1
Solving these two equations , we get : x= 1/80 and y= 1/80
Therefore B's 1 day work = 1/80
Hence,B alone shall finish the whole work in 80 days
M x T / W = Constant
where, M= Men (no. of men)
T= Time taken
W= Work load
So, here we apply
M1 x T1/ W1 = M2 x T2 / W2
Given that, M1 = 4 men, T1 = 7 hours ; T2 = 2 hours, we have to find M2 =?
Note that here, W1 = W2 = 1 road, ie. equal work load.
Clearly, substituting in the above equation we get, M2 = 14 men.
A + B= 70%
B + C =50%
=> B= 20% A= 50% and C=30%
Hence A is most efficient
Let efficiency of every man and every woman be 'm' unit/day and 'w' unit/day respectively
15×12×m = 10×16×w
? m/w = 8/9
Total work = 15 × 12 × 9 = 1620 units
In 2 days, total work done = 15 x 9 + 16 x 8 = 263 units
So, in 10 days work done will be = 263 × 5 = 1315 units
Remaining work will be done in = (1620-1315)/(15×8) = 5/2 days
Total days = 10 5/2 days.
(A+B+C)'s 1 day's work = (1/24 + 1/6 + 1/12) = 7/24
so, A,B and C together will complete the work in 24/7 days.
Combined efficiency of all the three boats = 60 passenger/trip
Now, consider option(a)
15 trips and 150 passengers means efficiency of B1 = 10 passenger/trip
which means in carrying 50 passengers B1 must has taken 5 trips. So the rest trips equal to 5 (10-5 = 5) in which B2 and B3 together carried remaining 250 (300 - 50 = 250) Passengers.
Therefore the efficiency of B2 and B3 = 250/5 = 50 passenger/trip
Since, the combined efficiency of B1, B2 and B3 is 60. Which is same as given in the first statement hence option(a) is correct.
From the given data,
=> (2 M + 3W) 8 = (3M + 2W)7
=> 16M + 24W = 21M + 14 W
=> 10W = 5M
=> 2W = M
=> 14W × ? = 7W × 8
? = 4 days
Given that
(10M + 15W) x 6 days = 1M x 100 days
=> 60M + 90W = 100M
=> 40M = 90W
=> 4M = 9W.
From the given data,
1M can do the work in 100 days
=> 4M can do the same work in 100/4= 25 days.
=> 9W can do the same work in 25 days.
=> 1W can do the same work in 25 x 9 = 225 days.
Hence, 1 woman can do the same work in 225 days.
A can do the work = 18 days
B can do the work = 18/2 = 9 days
(A + B)'s 1 day work = 1/18 + 1/9 = 1/6
=> In 3 days = 3x1/6 = 1/2 work is completed.
Let 'B' alone can do the work in 'x' days
6/30 + 18/x = 1
=> x = 22.5
1/30 + 1/22.5 = 7/90
=> 90/7 = 12 6/7 days
Amit did the work in 56 days =
Therefore, Rest work 17/45 was done by Amit and Bharath = = 8 days
( since Amit and Bharath do the work in one day = )
Comments
There are no comments.Copyright İCuriousTab. All rights reserved.