If 2 men and 3 women can do a piece of work in 8 days and 3 men and 2 women in 7 days. In how many days can the work be done by 5 men and 4 women working together?

Correct Answer: 4 days

Explanation:

From the given data,


=> (2 M + 3W) 8 = (3M + 2W)7


=> 16M + 24W = 21M + 14 W


=> 10W = 5M


=> 2W = M


=> 14W × ? = 7W × 8


? = 4 days