Construction activity sequence — choose the meaningful order Items: a. Foundation b. Plastering c. Building d. Painting

Verbal Reasoning Logical Sequence of Words Difficulty: Easy
Choose an option
  • A
    a, b, c, d
  • B
    a, c, b, d
  • C
    c, a, b, d
  • D
    c, a, d, b

Answer

Correct Answer: a, c, b, d

Explanation

Introduction / Context:Building construction follows a predictable pipeline from groundwork to finishes.

Given Data / Assumptions:Foundation precedes structural works; plastering precedes painting.

Concept / Approach:Place structural prerequisites first, cosmetic finishes last.

Step-by-Step Solution:Foundation (a) → Building/structure (c) → Plastering (b) → Painting (d).

Why Other Options Are Wrong:They place finishes before structure or foundation.

Final Answer:a, c, b, d