Difficulty: Easy
Correct Answer: a, c, b, d
Explanation:
Introduction / Context:
Building construction follows a predictable pipeline from groundwork to finishes.
Given Data / Assumptions:
Foundation precedes structural works; plastering precedes painting.
Concept / Approach:
Place structural prerequisites first, cosmetic finishes last.
Step-by-Step Solution:
Foundation (a) → Building/structure (c) → Plastering (b) → Painting (d).
Why Other Options Are Wrong:
They place finishes before structure or foundation.
Final Answer:
a, c, b, d