House construction (logical build order): Arrange— a. Plastering, b. Painting, c. Foundation, d. Walls, e. Ceiling.

Difficulty: Easy

Correct Answer: c, d, e, a, b

Explanation:


Introduction / Context:
Building construction proceeds from structural base to finishes.


Given Data / Assumptions:

  • Foundation first; then walls; then ceiling/roof structure; then internal finishes like plastering; finally painting.


Concept / Approach:
Arrange by structural dependency and finish sequencing.


Step-by-Step Solution:

Foundation (c) → Walls (d) → Ceiling (e) → Plastering (a) → Painting (b).


Verification / Alternative check:
Matches typical site workflows.


Why Other Options Are Wrong:
They attempt finishing before structure.


Common Pitfalls:
Painting before plastering.


Final Answer:
c, d, e, a, b