Concrete construction practices: construction joints are generally provided at which of the following positions or conditions?

Civil Engineering Concrete Technology Difficulty: Easy
Choose an option
  • A
    in concrete wall at sill level of windows
  • B
    where bending moment and shear force are small
  • C
    where a member is supported by another member
  • D
    at 18 m spacing in very large structures
  • E
    all the above

Answer

Correct Answer: all the above

Explanation

Introduction / Context:Construction joints are planned discontinuities in concrete work to accommodate interruptions. Proper placement avoids structural weakness and ensures load transfer.

Given Data / Assumptions:

  • Monolithic construction is ideal but often impractical.
  • Joint positions are chosen to minimize adverse effects.

Concept / Approach:Joints should be at locations of minimum stress (low BM and SF), at support points, or at natural breaks (like window sills). In large continuous structures, spacing rules like 18 m apply.

Step-by-Step Solution:(a) Walls: sill level joints are convenient and aesthetic.(b) Structural members: joints at low stress regions are safe.(c) Supports: natural cut-off point.(d) Long structures: spacing provides control.Thus, all apply.

Verification / Alternative check:IS 456 provides guidance for joint placement at low stress zones and architectural breaks.

Why Other Options Are Wrong:

  • No option is wrong; all are valid placement criteria.

Common Pitfalls:

  • Providing joints at high stress regions, leading to cracks or leakage.

Final Answer:all the above