Shantanu completes five-eighths (5/8) of a job in 20 days at a constant pace. At this rate, how many more days are needed to finish the remaining work?

Difficulty: Easy

Correct Answer: 12 days

Explanation:


Introduction:
When a fraction of work is completed in a given time at constant rate, we can derive the worker’s rate and project the time for the remaining fraction. This is a direct proportionality: time is proportional to the fraction of work at a fixed rate.


Given Data / Assumptions:

  • Fraction completed: 5/8 in 20 days.
  • Constant work rate throughout.
  • Remaining fraction = 3/8.


Concept / Approach:
Rate r = (work done) / (time) = (5/8) / 20 = 1/32 job per day. Remaining time = (remaining work)/(rate). Compute and convert to days as an integer if it divides exactly (it does here).


Step-by-Step Solution:

r = (5/8)/20 = 5/160 = 1/32 job/day Remaining work = 1 − 5/8 = 3/8 Time needed = (3/8) / (1/32) = (3/8) * 32 = 12 days


Verification / Alternative check:
Proportion: If 5/8 takes 20 days, then 1/8 takes 4 days (divide by 5). Hence 3/8 takes 12 days (multiply by 3). Same result, quicker mental check.


Why Other Options Are Wrong:
6, 5, 8, 18 days do not match the linear scaling implied by a constant rate from 5/8 in 20 days.


Common Pitfalls:
Adding times incorrectly or confusing the completed fraction with the remaining one. Always compute the residual fraction carefully.


Final Answer:
12 days

More Questions from Unitary Method

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion