Difficulty: Easy
Correct Answer: 12 days
Explanation:
Introduction: When a fraction of work is completed in a given time at constant rate, we can derive the worker’s rate and project the time for the remaining fraction. This is a direct proportionality: time is proportional to the fraction of work at a fixed rate.
Given Data / Assumptions:
Concept / Approach: Rate r = (work done) / (time) = (5/8) / 20 = 1/32 job per day. Remaining time = (remaining work)/(rate). Compute and convert to days as an integer if it divides exactly (it does here).
Step-by-Step Solution:
r = (5/8)/20 = 5/160 = 1/32 job/day Remaining work = 1 − 5/8 = 3/8 Time needed = (3/8) / (1/32) = (3/8) * 32 = 12 daysVerification / Alternative check: Proportion: If 5/8 takes 20 days, then 1/8 takes 4 days (divide by 5). Hence 3/8 takes 12 days (multiply by 3). Same result, quicker mental check.
Why Other Options Are Wrong: 6, 5, 8, 18 days do not match the linear scaling implied by a constant rate from 5/8 in 20 days.
Common Pitfalls: Adding times incorrectly or confusing the completed fraction with the remaining one. Always compute the residual fraction carefully.
Final Answer: 12 days
Discussion & Comments