Biochemical stabilization timeline: Approximately how long does it take for complete stabilization (ultimate BOD exertion) of organic matter in polluted water at standard conditions used in design problems?

Civil Engineering Water Supply Engineering Difficulty: Easy
Choose an option
  • A
    5 days
  • B
    10 days
  • C
    20 days
  • D
    30 days
  • E
    40 days

Answer

Correct Answer: 20 days

Explanation

Introduction / Context:Biochemical Oxygen Demand (BOD) reflects the oxygen required by microorganisms to oxidize biodegradable organic matter. While the standard BOD test is 5 days at 20°C (BOD5), full biochemical stabilization (ultimate BOD) takes longer.

Given Data / Assumptions:

  • Standard wastewater engineering convention at 20°C.
  • Ultimate BOD approaches asymptote over several weeks.

Concept / Approach:BOD exertion follows first-order kinetics: BOD(t) = L0 * (1 − e^(−k*t)), where L0 is ultimate BOD and k is the deoxygenation rate constant. At 5 days, only a fraction of L0 is exerted; practical “complete stabilization” for design approximations is taken near 20 days for typical domestic wastewater at 20°C.

Step-by-Step Solution:Recognize BOD5 is a standard test period, not full stabilization.Use the conventional design approximation: ultimate exertion within roughly 20 days at 20°C.Select the corresponding option.

Verification / Alternative check:Plotting BOD kinetics with a representative k (say 0.23 day^-1 at 20°C) shows BOD exerted by 20 days is very close to L0, supporting the rule-of-thumb period.

Why Other Options Are Wrong:

  • 5 or 10 days: too short for ultimate BOD; used for standard sampling and reporting.
  • 30 or 40 days: beyond the customary engineering reference; offers little additional design insight.

Common Pitfalls:

  • Equating BOD5 with complete stabilization—this underestimates oxygen demand for long retention processes.

Final Answer:20 days

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion