According to standard observational practice in India, at what local time is the daily rainfall typically recorded and entered in the gauge register?

Civil Engineering Water Resources Engineering Difficulty: Easy
Choose an option
  • A
    8 A.M.
  • B
    12 Noon
  • C
    4 P.M.
  • D
    8 P.M.

Answer

Correct Answer: 8 A.M.

Explanation

Introduction / Context:Consistency in rainfall observation time is essential for hydrologic data quality and inter-station comparability. India follows a standard observation hour for daily totals.

Given Data / Assumptions:

  • Daily rain gauge readings must be taken at a fixed local time.
  • Question asks the conventional time used in India.

Concept / Approach:Indian meteorological and hydrological services traditionally observe daily precipitation at 8 A.M. local time to define the 24-hour accumulation period.

Step-by-Step Solution:Identify the standard practice per national guidelines.Record the rainfall depth accumulated during the previous 24 hours at 8 A.M.Enter the measured value into the daily register for data continuity.

Verification / Alternative check:Hydrology lab manuals and rain gauge operation instructions in India specify the 8 A.M. observation.

Why Other Options Are Wrong:

  • Noon, 4 P.M., 8 P.M.: not standard for daily recording in India.

Common Pitfalls:

  • Confusing synoptic observation hours with daily rainfall recording conventions.

Final Answer:8 A.M.