More Questions from Waste Water Engineering

What governs the longitudinal gradient (slope) selected for sanitary sewers? Pick the best statement describing the factors that primarily determine sewer grade.

Civil Engineering Waste Water Engineering Difficulty: Easy
Choose an option
  • A
    velocity of flow
  • B
    diameter of the sewer
  • C
    discharge
  • D
    all the above.
  • E
    none of these

Answer

Correct Answer: all the above.

Explanation

Introduction / Context:The grade (slope) of a gravity sewer must be chosen to achieve self-cleansing velocities while preventing excessive velocities that could cause scouring and structural issues. Because velocity is a function of hydraulic radius and slope for a given discharge (e.g., via Manning’s equation), several variables co-determine the selected slope.

Given Data / Assumptions:

  • Gravity flow in partially full circular conduits.
  • Use of empirical relations like Manning’s V = (1/n) R^(2/3) S^(1/2).
  • Target self-cleansing velocity, commonly around 0.6–0.75 m/s for sanitary sewers (varies by standard).

Concept / Approach:

For a specified design discharge, the chosen diameter and slope together set the hydraulic radius and thus velocity. Conversely, a required self-cleansing velocity dictates a minimum slope for a chosen diameter and expected flow. Therefore, all three—discharge, diameter, and target velocity—are linked and jointly determine the gradient.

Step-by-Step Solution:

Start from Manning: V = (1/n) R^(2/3) S^(1/2).Given Q, choose D; compute A and R for partial flow.Solve for S that yields V ≥ V_min (self-cleansing), respecting V ≤ V_max (no scouring).Hence slope depends on velocity target, diameter, and discharge.

Verification / Alternative check:

Design tables present recommended minimum slopes as a function of pipe size and anticipated flow to achieve self-cleansing—confirming multi-dependence.

Why Other Options Are Wrong:

(a), (b), and (c) alone do not fully specify the slope; the integrated view in (d) is correct.

Common Pitfalls:

Choosing minimal slopes without checking low-flow velocities; ignoring roughness n changes over time due to slime or sediment deposition.

Final Answer:

all the above.