Difficulty: Easy
Correct Answer: all the above
Explanation:
Introduction / Context:
Construction joints are planned discontinuities in concrete work to accommodate interruptions. Proper placement avoids structural weakness and ensures load transfer.
Given Data / Assumptions:
Concept / Approach:
Joints should be at locations of minimum stress (low BM and SF), at support points, or at natural breaks (like window sills). In large continuous structures, spacing rules like 18 m apply.
Step-by-Step Solution:
(a) Walls: sill level joints are convenient and aesthetic.(b) Structural members: joints at low stress regions are safe.(c) Supports: natural cut-off point.(d) Long structures: spacing provides control.Thus, all apply.
Verification / Alternative check:
IS 456 provides guidance for joint placement at low stress zones and architectural breaks.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
all the above