Difficulty: Easy
Correct Answer: 2, 3, 1, 4, 5
Explanation:
Introduction / Context:
We select a coherent order given only these items (walls, etc., are omitted in the options).
Given Data / Assumptions:
Foundation precedes superstructure; basic flooring preparation comes early; openings (windows/ventilators) are fitted before final roofing in this simplified sequence.
Concept / Approach:
Start from base, then internal surface, then openings, and finally the covering.
Step-by-Step Solution:
Verification / Alternative check:
Among the given choices, this is the most construction-plausible flow.
Why Other Options Are Wrong:
They start with floor before foundation or place windows before base—logically inconsistent.
Common Pitfalls:
Assuming missing items (walls) must appear; stick to given elements.
Final Answer:
2, 3, 1, 4, 5