Difficulty: Easy
Correct Answer: $80
Explanation:
Introduction / Context:
When a contractor hires help, the fair split of the fixed amount is proportional to the actual work contributed by each person. We compute how much of the job A completed in 6 days and assign the remainder to B.
Given Data / Assumptions:
Concept / Approach:
Work done by A in 6 days = 6 * (1/8) = 3/4 of the job. Therefore B must have done the remaining 1/4. Payment is split 3/4 to A and 1/4 to B.
Step-by-Step Solution:
A’s contribution = 3/4 of jobB’s contribution = 1/4 of jobB’s share = 1/4 * $320 = $80
Verification / Alternative check:
A’s share = 3/4 * $320 = $240; sum $240 + $80 = $320.
Why Other Options Are Wrong:
$120 and $100 overpay B; $60 underpays; $240 is A’s share.
Common Pitfalls:
Splitting by days worked instead of fraction of total job accomplished.
Final Answer:
$80
Discussion & Comments