Difficulty: Easy
Correct Answer: 14 hours
Explanation:
Introduction / Context:
Let a, b, c be the hourly fill rates of A, B, and C. The joint rate and the two-phase timeline give two equations, from which we isolate c and invert to get C’s solo time.
Given Data / Assumptions:
Concept / Approach:
Work done in first 2 hours = 2 * (1/6) = 1/3. Remaining = 2/3. Thus (a + b) * 7 = 2/3 ⇒ a + b = 2/21. Then c = 1/6 − 2/21.
Step-by-Step Solution:
Verification / Alternative check:
Check totals: First 2 h give 1/3; then 7 h at 2/21 give 14/21 = 2/3; total 1 job.
Why Other Options Are Wrong:
10/12/16 hours do not match the derived c = 1/14.
Common Pitfalls:
Confusing “7 hours to finish” as total time rather than the second phase duration.
Final Answer:
14 hours
Discussion & Comments