Difficulty: Easy
Correct Answer: 12 hours
Explanation:
Introduction / Context:
This is a two-phase problem: a mixed phase with both inlets and the outlet, followed by an inlet-only phase. Compute the fraction completed in the first 10 hours, then finish with A and B only.
Given Data / Assumptions:
Concept / Approach:
Phase 1 work = 10 * (1/15 + 1/20 − 1/25). Phase 2 time = (remaining) / (1/15 + 1/20). Sum both phases for total time.
Step-by-Step Solution:
Verification / Alternative check:
Back-substitution confirms totals reach exactly 1 job.
Why Other Options Are Wrong:
13 1/2 / 16 / 18 hours do not match the exact two-phase computation.
Common Pitfalls:
Dropping the outlet term during Phase 1 or miscomputing the remaining fraction.
Final Answer:
12 hours
Discussion & Comments