Difficulty: Easy
Correct Answer: 36
Explanation:
Introduction:
With identical workers at a constant rate, total work (in man-days) is fixed. Changing the number of men scales time inversely. We simply compute the total man-days from the first scenario and divide by the new headcount to get the new duration.
Given Data / Assumptions:
Concept / Approach:
Total work W = 12 * 24 man-days. With 8 men, days needed D = W / 8. This is a direct inverse proportion of time with respect to the number of workers for fixed total work and constant efficiency.
Step-by-Step Solution:
Verification / Alternative check:
Compare ratios: time ∝ 1/men, so D_new = 24 * (12/8) = 24 * 1.5 = 36, consistent with the man-day calculation.
Why Other Options Are Wrong:
28, 48, 52, or 32 days do not preserve the constant man-days of 288 for 8 men.
Common Pitfalls:
Using direct proportion (time increasing with men) instead of inverse, or forgetting the job remains identical in scope.
Final Answer:
36
Discussion & Comments