Startup cost allowance in fixed-capital planning As a rule of thumb in chemical plant estimating, the maximum production start-up cost to bring a new plant on-stream is approximately what percent of the fixed capital cost?
-
A1
-
B5
-
C10
-
D30
Answer
Correct Answer: 5
Explanation
Introduction / Context:Bringing a new process unit into operation requires pre-commissioning, operator training, initial off-spec production, extra utilities, and consumables. Estimators often include a provisional allowance for “production start-up cost” as a fraction of fixed capital when detailed data are unavailable.
Given Data / Assumptions:
- Fixed capital cost is already established.
- Typical commodity chemical plant under normal complexity.
- Seeking a common rule-of-thumb maximum allowance figure.
Concept / Approach:Textbook heuristics commonly cite a start-up allowance in the range of about 3–5% of fixed capital cost for conventional plants, occasionally higher for complex facilities. Using the conservative “maximum of typical” values, 5% is widely used in screening estimates.
Step-by-Step Solution:
Recall standard estimating ranges for start-up costs.Select the upper representative value used in many preliminary estimates.Answer: 5 percent of fixed capital cost.Verification / Alternative check:Comparisons with historical project closeouts show start-up costs clustering in low single-digit percentages of fixed capital for typical chemical units.
Why Other Options Are Wrong:
- 1%: Often too low, risks under-provisioning for training/commissioning.
- 10% or 30%: Excessive for ordinary plants; such high allowances imply unusual complexity or major schedule/capability risks.
Common Pitfalls:Confusing start-up cost with working capital; ignoring that specialty or first-of-a-kind plants may require larger allowances than standard heuristics.
Final Answer:5