Difficulty: Medium
Correct Answer: Risk analysis is the process of identifying and evaluating potential problem areas in the product, combining the likelihood of failure with its impact; severity reflects impact, priority reflects urgency, and together they guide which risks and defects should be addressed first
Explanation:
Introduction / Context:
Software projects rarely have unlimited time and budget, so testers must focus their effort where it matters most. Risk analysis is a technique used to decide which features, scenarios and defects pose the greatest threat to the success of the project. Defect severity and priority are closely related concepts that help operationalize risk decisions during defect triage.
Given Data / Assumptions:
Concept / Approach:
Risk analysis starts by identifying key assets and features, such as safety critical functions, financial calculations or security sensitive components. For each risk item, testers estimate the likelihood of failure and the potential level of damage. High risk areas receive more test depth. When defects are found, their severity and priority are assigned in line with this risk view: a highly severe defect in a critical area with high likelihood of occurrence naturally gets high priority.
Step-by-Step Solution:
Define risk as risk = likelihood * impact, where both factors can be qualitative or quantitative.
During planning, identify features or technical areas where failure would have major consequences, such as data loss, security breaches or safety issues.
Assign higher test effort, stronger techniques and more automation to these high risk areas.
When a defect is discovered, set severity based on impact: for example, does it cause system crash, incorrect results, minor cosmetic issues or something in between?
Set priority based on how urgently the defect should be fixed, considering release deadlines, workarounds and business commitments. Risk analysis provides the context for these decisions.
Verification / Alternative check:
In real projects, you will notice that severe defects in low risk areas might be tolerated for a short time if there are simple workarounds, while lower severity defects in high risk areas can still get high priority. This shows how risk thinking, severity and priority interact. Test managers can also use risk matrices that combine impact and likelihood ratings to decide test depth and triage rules.
Why Other Options Are Wrong:
Option b incorrectly reduces risk analysis to defect counting and treats severity and priority as cosmetic labels, which ignores their decision making role.
Option c splits risk analysis and severity or priority into unrelated phases, while in practice they are used together throughout the lifecycle.
Option d is wrong because risk analysis does not remove the need for severity and priority; rather, it informs how they should be assigned.
Common Pitfalls:
A common mistake is to treat all tests and all defects as equally important. Another pitfall is to assign severity based only on who reported the defect rather than its real impact. To avoid these issues, teams should define clear severity and priority criteria that are aligned with risk analysis and business goals.
Final Answer:
Risk analysis in testing is the process of identifying and evaluating potential failures by combining likelihood and impact, and it is closely linked to defect severity (impact) and priority (urgency), which together determine which risks and defects deserve the most attention.