Difficulty: Medium
Correct Answer: 4 days
Explanation:
Introduction / Context:
This question is a time and work scenario framed in terms of cutting nuts. Two workers, Ram and Hari, work together for some time and then one of them continues alone. We are given the total output and must deduce individual rates to then find how long Hari alone would take to cut a specific quantity of nuts. Such problems connect real life situations of shared work and are common in aptitude tests.
Given Data / Assumptions:
Concept / Approach:
We treat the cutting of nuts as a work rate problem in kilograms per day. First we find the combined daily rate of Ram and Hari. Then, using the total production and additional days that Ram works alone, we calculate Ram individual rate. Subtracting Ram rate from the combined rate gives Hari rate. Finally, we use Hari rate to find the time required for him to cut 10 kilograms alone. This is a direct application of rate equations.
Step-by-Step Solution:
Step 1: Combined production of Ram and Hari is 12 kilograms in 2 days.
Step 2: Combined daily rate of Ram and Hari = 12 / 2 = 6 kilograms per day.
Step 3: For the first 5 days, they work together and produce 5 * 6 = 30 kilograms.
Step 4: Total nuts cut is 58 kilograms, so remaining after 5 days = 58 - 30 = 28 kilograms.
Step 5: Ram alone cuts these 28 kilograms in 8 days.
Step 6: Ram daily rate = 28 / 8 = 3.5 kilograms per day.
Step 7: Combined daily rate of Ram and Hari is 6 kilograms per day, so Hari daily rate = 6 - 3.5 = 2.5 kilograms per day.
Step 8: Time taken by Hari alone to cut 10 kilograms = 10 / 2.5 = 4 days.
Verification / Alternative check:
We can verify by reconstructing the entire story using the found rates. On each day of the first 5 days, Ram cuts 3.5 kilograms and Hari cuts 2.5 kilograms, so together they cut 6 kilograms. In 5 days, they cut 30 kilograms. Then, Ram alone working 8 days at 3.5 kilograms per day cuts 28 kilograms. Thus, total nuts cut = 30 + 28 = 58 kilograms, which matches the given total. This confirms that the calculated rates and the final answer are correct.
Why Other Options Are Wrong:
If Hari took only 1, 2, or 3 days to cut 10 kilograms, his rate would be 10, 5, or 3.33 kilograms per day respectively, which are inconsistent with the combined rate and Ram rate. If he took 5 days, his rate would be only 2 kilograms per day, which would not yield a combined rate of 6 kilograms per day when added to Ram rate of 3.5 kilograms per day. Only 4 days gives Hari rate of 2.5 kilograms per day that fits all given conditions.
Common Pitfalls:
Some learners may assume that both workers are equally efficient and simply divide totals by two, which is not supported by the data. Others might forget to remove the contribution of the first phase when two people worked together and try to directly distribute the total among the individuals. The correct method is to find combined rate, then individual rate from the second phase, and finally deduce the other worker rate.
Final Answer:
Hari alone would take 4 days to cut 10 kilograms of nuts.
Discussion & Comments