  • 1. Pick up the item of work not included in the plinth area estimate

  • Options
  • A. Wall thickness
  • B. Room area
  • C. Verandah area
  • D. W.C. area
  • E. Courtyard area.
  • Discuss
  • 2. If tensile stress of a steel rod of diameter D is 1400 kg/cm2 and bond stress is 6 kg/cm2, the required bond length of the rod is

  • Options
  • A. 30 D
  • B. 40 D
  • C. 50 D
  • D. 53 D
  • E. 59 D
  • Discuss
  • 3. The correct prismoidal formula for volume is

  • Options
  • A. D [first area + last area + ? Even area + 2 ? odd areas]
  • B. [first area + last area + 4 ? Even area + 2 ? odd areas]
  • C. [first area + last area + 2 ? Even area + 4 ? odd areas]
  • D. [first area + last area + 2 ? Even area + 4 ? odd areas].
  • Discuss
  • 4. The brick work is measured in sq metre, in case of

  • Options
  • A. Honey comb brick work
  • B. Brick flat soling
  • C. Half brick walls or the partition
  • D. All the above.
  • Discuss
  • 5. The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is

  • Options
  • A. L + 0.42 d
  • B. L + 2 x 0.42 d
  • C. L - 0.42 d
  • D. L - 2 x 0.4 d
  • Discuss
  • 6. If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by

  • Options
  • A. Mid-section formula
  • B. Trapezoidal formula
  • C. Prismoidal formula
  • D. All the above.
  • Discuss
  • 7. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

  • Options
  • A. 26, 000 m3
  • B. 26, 500 m3
  • C. 27, 000 m3
  • D. 27, 500 m3
  • Discuss
  • 8. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken

  • Options
  • A. 1.80 litres for 5 to 10 users
  • B. 1.20 litres for 15 users
  • C. 1.35 for 20 users
  • D. All the above.
  • Discuss
  • 9. The main factor to be considered while preparing a detailed estimate, is

  • Options
  • A. Quantity of the materials
  • B. Availability of materials
  • C. Transportation of materials
  • D. Location of site and local labour charges
  • E. All the above.
  • Discuss
  • 10. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

  • Options
  • A. Excavation
  • B. Surface dressing
  • C. Cutting
  • D. Surface excavation.
  • Discuss