Estimating and Costing problems


  • 1. The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is
    Civil Engineering Estimating and Costing: The reduced levels of points, 30 metres apart along the longitudinal section of a road portion betwe

  • Options
  • A. (6 + 15) chains
  • B. (6 + 12) chains
  • C. (6 + 18) chains
  • D. None of these.
  • Discuss
  • 2. Pick up the incorrect statement from the following:

  • Options
  • A. Dimensions are measured to the nearest 0.01 m
  • B. Areas are measured to the nearest 0.01 sq.m
  • C. Cubic contents are measured to the nearest 0.1 cm m
  • D. Weights are measured to the nearest 0.001 tonnes
  • Discuss
  • 3. Pick up the correct statement from the following:

  • Options
  • A. The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
  • B. The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
  • C. The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
  • D. All the above.
  • Discuss
  • 4. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and

  • Options
  • A. breadth of the wall
  • B. half breadth of wall on each side
  • C. one fourth breadth of wall on each side
  • D. None of these.
  • Discuss
  • 5. According to ISI method of measurement, the order of the sequence is

  • Options
  • A. Length, breadth, height
  • B. Breadth, length, height
  • C. Height, length, breadth
  • D. None of these.
  • Discuss
  • 6. The inspection pit or chamber is a manhole provided in a base drainage system

  • Options
  • A. at every change of direction
  • B. at every change of gradient
  • C. at every 30 m intervals
  • D. at the point where vertical soil pipe joins the house drain
  • E. All the above.
  • Discuss
  • 7. The most reliable estiamte is

  • Options
  • A. Detailed estimate
  • B. Preliminary estimate
  • C. Plinth area estimate
  • D. Cube rate estimate
  • E. None of these.
  • Discuss
  • 8. The measurement is not made in square metres in case of

  • Options
  • A. D.P.C. (Damp proof course)
  • B. Form works
  • C. Concrete Jaffries
  • D. R.C. Chhajja.
  • Discuss
  • 9. The expected out turn of 12 mm plastering with cement mortar is

  • Options
  • A. 2.5 sq m
  • B. 4.0 sq m
  • C. 6.0 sq m
  • D. 8.0 sq m
  • E. 10 sq m
  • Discuss
  • 10. The area of a sloping surface of a protective embankment of mean height d, side slopes S : 1 and length L is

  • Options
  • A. d x d x s
  • B. d2 x (ds)2
  • C. L.D 1 + s2
  • D. 2 LD 1 + s2
  • Discuss