Work done = 1/3
Remaining work = 2/3
So for double work in same days we need double number of people i.e. 40.
So, 20 men will be increased.
A's 1 day's work = (1/15 - 1/20) = 1/60
? A alone can finish it in 60 days.
B's one day's work = (1/6 - 1/9) = 1/18
? B alone can finish it in 18 days.
(A + B)'s 1 day's work = 1/18
(B + C)'s 1 day's work = 1/24
(A + C)'s 1 day's work = 1/36
Adding 2 (A + B + C)'s 1 day's work = (1/18 + 1/24 + 1/36) = 1/8
? (A + B + C)'s day's work = 1/16
Hence, all working together can finish it in 16 days.
? [(A + B) + (B + C) + (C + A)]'s 1 day's work = (1/12 + 1/15 + 1/20) = 1/5
? 2(A + B + C)'s 1 days work = 1/5
? (A + B + C)'s 1 day's work = 1/10
&rArr A's 1 day's work = (1/10 - 1/15) = 1/30
? A alone can finish it in 30 days.
(A + B)'s 1 day's work = (1/30 + 1/40) = 7/120
? Time taken by both to finish the work = 120/7days = 171/7 days
? 1/3 of work is done by A in 5 days.
? Whole work will be done by A in 15 days.
? 2/3 of work is done by B in 10 days.
Whole work will be done by B in 10 x (5/2) i.e., 25days
? (A + B)'s 1 day's work = (1/15 + 1/25) = 8/75
So, both together can finish it in 75/8 days, i.e., 93/8days.
B's 9 day's work = 9 x (1/12) = 3/4
Remaining work = (1 - 3/4) = 1/4
1/4 work is done by A in = 20 x (1/4) = 5 days.
Required time taken by B to complete the work = xy / x - y
[Here x = 12 and y = 8]
? required time = (12 x 8) / (12 - 8) = 96/4 = 24 days
Required time taken to complete the work by both together = x y / x + y
(Here x = 8 and y = 4)
? Required time = (8 x 4)/(8 + 4) = 32/12 = 22/3 hours
Copyright ©CuriousTab. All rights reserved.