Number of pages typed by Adam in 1 hour = 36/6 = 6
Number of pages typed by Smith in 1 hour = 40/5 = 8
Number of pages typed by both in 1 hour = (6 + 8) = 14
Time taken by both to type 110 pages = (120 * 1/14) =
= 8 hrs 34 min.
One day work of 6 boys and 8 girls is given as 6b + 8g = 1/10 -------->(I)
One day work of 26 boys and 48 women is given as 26b + 48w = 1/2 -------->(II)
Divide both sides by 2 in (I) and then multiply both sides by 5
Now we get, 15b + 20g = 1/4.
Therefore, 15 boys and 20 girls can do the same work in 4 days.
1/3 ---- 8
1 -------?
Hari can do total work in = 24 days
As satya is 60% efficient as Hari, then
Satya = 1/24 x 60/100 = 1/40
=> Satya can do total work in 40 days
1 ----- 40
2/3 ---- ? => 26 2/3 days.
Let the Efficiency of pavan be E(P)
Let the Efficiency of sravan be E(S)
Here Work W = LCM(25,20) = 100
Now, E(P+2S) = 100/25 = 4 ....(1)
E(2P+S) = 100/20 = 5 ....(2)
Hence, from (1) & (2) we get
E(S) = 1
=> Number of days Savan alone work to complete the work = 100/1 = 100 days.
Ratio of efficiencies of Priya and Sai is
Sai : Priya = 160 : 100 = 8 : 5
Given Priya completes the work in 16 days
Let number of days Sai completes the work be 'd'
=> 5×16 = 8×d
d = 10 days.
Therefore, number of days Sai completes the work is 10 days.
Efficiency of kaushalya = 5%
Efficiency of kaikeyi = 4%
Thus, in 10 days working together they will complete only 90% of the work.
[(5+4)*10] =90
Hence, the remaining work will surely done by sumitra, which is 10%.
Thus, sumitra will get 10% of Rs. 700, which is Rs.70
Given,
P can fill in 12 hrs
Q can fill in 15 hrs
R can fill in 20 hrs
=> Volume of tank = LCM of 12, 15, 20 = 60 lit
=> P alone can fill the tank in 60/12 = 5 hrs
=> Q alone can fill the tank in 60/15 = 4 hrs
=> R alone can fill the tank in 60/20 = 3 hrs
Tank can be filled in the way that
(P+Q) + (P+R) + (P+Q) + (P+R) + ....
=> Tank filled in 2 hrs = (5+4) + (5+3) = 9 + 8 = 17 lit
=> In 6 hrs = 17 x 6/2 = 51 lit
=> In 7th hr = 51 + (5+4) = 51 + 9 = 60 lit
=> So, total tank will be filled in 7 hrs.
Work done by P and Q in the first two hours, working alternately
= First hour P + Second hour Q
work is completed in 2 hours
Then, the total time required to complete the work by P and Q working alternately=2 x 3= 6hours
Thus, work will be completed at 3pm.
Amount of work K can do in 1 day = 1/16
Amount of work L can do in 1 day = 1/12
Amount of work K, L and M can together do in 1 day = 1/4
Amount of work M can do in 1 day = 1/4 - (1/16 + 1/12) = 3/16 ? 1/12 = 5/48
=> Hence M can do the job on 48/5 days = 9 (3/5) days
Given the ratio of efficiencies of P, Q & R are 3 : 8 : 5
Let the efficiencies of P, Q & R be 3x, 8x and 5x respectively
They can do work for 12 days.
=> Total work = 12 x 16x = 192x
Now, the required time taken by Q to complete the job alone = days.
Copyright ©CuriousTab. All rights reserved.