Time study calculations: role of the rating factor In time study, after observing cycles, what does multiplying by the performance rating (rating factor) determine? Choose the correct outcome.

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    Standard time of a job
  • B
    Merit rating of the worker
  • C
    Fixation of incentive rate
  • D
    Normal time of a worker

Answer

Correct Answer: Normal time of a worker

Explanation

Given/ConceptObserved Time × Rating Factor = Normal Time. Then Standard Time = Normal Time × (1 + Allowances).

Step-by-step1) Observe cycle times → average → representative time.2) Apply rating factor → normal time.3) Add allowances → standard time.

Final AnswerNormal time of a worker