Two-person team timing: A man and a boy together finish a job in 24 days. If, for the last 6 days, the man works alone and the job finishes in 26 days total, how long would the boy take alone?

Difficulty: Medium

Correct Answer: 72 days

Explanation:


Introduction / Context:
Express daily work as rates. The pair’s joint rate is known from the 24-day completion. The altered schedule provides a second equation involving the man’s solo work in the last 6 days. Solve to find each individual rate, then invert to get solo times.


Given Data / Assumptions:

  • (Man + Boy) complete in 24 days ⇒ m + b = 1/24 job/day.
  • In the 26-day schedule, first 20 days both work; last 6 days man works alone.


Concept / Approach:
Total work equals work in first 20 days plus work in last 6 days. Use m + b and the 26-day completion to find m, then compute b = (1/24 − m). Boy’s solo time = 1 / b days.


Step-by-Step Solution:

20(m + b) + 6m = 1 20*(1/24) + 6m = 1 ⇒ 20/24 + 6m = 1 ⇒ 5/6 + 6m = 1 6m = 1 − 5/6 = 1/6 ⇒ m = 1/36 b = 1/24 − 1/36 = (3 − 2)/72 = 1/72 ⇒ Boy alone takes 72 days


Verification / Alternative check:
Check rates: Together 1/24; man 1/36; boy 1/72. First 20 days: 20*(1/24) = 5/6. Last 6 days (man only): 6*(1/36) = 1/6. Total = 5/6 + 1/6 = 1 job. Valid.


Why Other Options Are Wrong:
73, 49, 62, 84 contradict the computed b = 1/72 job/day.


Common Pitfalls:
Assuming both worked for all 26 days or misallocating the last 6 days to both workers. Also, mixing times directly instead of using rates leads to errors.


Final Answer:
72 days

More Questions from Unitary Method

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion