Difficulty: Easy
Correct Answer: 3 2 4 1
Explanation:
Introduction / Context:
Tunnel planning begins long before excavation. An orderly initial survey sequence ensures that the alignment is first conceptualized on authoritative maps, refined by fixing obligatory control points (e.g., portals, shafts, curve points), physically connected by lines on the map and ground, and finally materialized at the site with permanent markers. This question checks understanding of that logical progression from desk study to field control.
Given Data / Assumptions:
Concept / Approach:
Good practice is to start with map-based preliminary setting to decide a viable corridor. Then, obligatory points are marked on the topo sheets. Next, the surveyor establishes control/connection between these fixed points by driving lines (joining them). Finally, the alignment is pegged on ground at the portal with permanent concrete pillars to serve as lasting benchmarks for subsequent detailed survey and construction layout.
Step-by-Step Solution:
Verification / Alternative check:
Reversing the order would either attempt to pillar a portal before the alignment is fixed, or join points that are not yet defined—both illogical. The selected sequence mirrors standard feasibility-to-field-transfer workflow.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
3 2 4 1
Discussion & Comments