Difficulty: Easy
Correct Answer: 0.9
Explanation:
Introduction / Context:
This is a straightforward work and time question involving a single worker. We are told how long the worker takes to complete the entire job and asked what fraction of the job remains after working for a shorter number of hours. It directly uses the concept of proportional completion of work over time for a constant rate worker.
Given Data / Assumptions:
Concept / Approach:
When a worker completes a job in T hours, in one hour the worker completes 1 / T of the job. Therefore, in t hours, the worker will complete t / T of the job. For this problem, we find the fraction of the job done in 7 hours and subtract this from 1 to obtain the incomplete fraction. The result is expressed as a decimal fraction, as shown in the options.
Step-by-Step Solution:
Step 1: Let the total work of building the wall be 1 unit.Step 2: Time required to complete the wall = 70 hours.Step 3: Therefore, in 1 hour, the mason completes 1 / 70 of the wall.Step 4: In 7 hours, the fraction of the wall completed = 7 * (1 / 70) = 7 / 70 = 1 / 10.Step 5: Fraction of the wall remaining = 1 - 1 / 10 = 9 / 10.Step 6: Express 9 / 10 as a decimal: 9 / 10 = 0.9.
Verification / Alternative check:
We can also note that 7 hours is exactly one tenth of the total required time, since 7 is 1 / 10 of 70. With a constant rate, in one tenth of the total time, the worker completes one tenth of the job. Thus 9 tenths remain, confirming that the fraction 0.9 is correct.
Why Other Options Are Wrong:
Common Pitfalls:
Some learners mistakenly divide the completed fraction as 7 / 70 and then forget to subtract from 1 to find what is left, or they confuse the fraction completed with the fraction remaining. Others might try to convert hours in an unnecessary way that complicates the calculation. The best approach is to work directly with fractions of the total time.
Final Answer:
The fraction of the wall still left to be built is 0.9.
Discussion & Comments