Difficulty: Medium
Correct Answer: 16 days
Explanation:
Introduction / Context:
This is a classic three worker time and work problem where the pairwise times for different pairs of workers are given. The goal is to determine the time required when all three workers collaborate. It involves solving a small system of equations based on work rates rather than times.
Given Data / Assumptions:
Concept / Approach:
Let the individual daily work rates of A, B and C be a, b and c units per day respectively. Then the combined rates for the given pairs are a + b, b + c and a + c. These three expressions correspond to 1 / 36, 1 / 24 and 1 / 18 respectively. By adding these three equations and simplifying, we can find the total rate a + b + c, and then compute the time taken by all three together as the reciprocal of this total rate.
Step-by-Step Solution:
Step 1: Let total work be 1 unit. Let daily work rates of A, B and C be a, b and c respectively.Step 2: From the data, we have three equations based on pairwise work:(i) a + b = 1 / 36(ii) b + c = 1 / 24(iii) a + c = 1 / 18Step 3: Add all three equations: (a + b) + (b + c) + (a + c) = 1 / 36 + 1 / 24 + 1 / 18.Step 4: On the left side, this becomes 2(a + b + c). So 2(a + b + c) = 1 / 36 + 1 / 24 + 1 / 18.Step 5: Find the sum on the right. The common denominator of 36, 24 and 18 is 72 or 360, but we can compute directly. For convenience, use 72: 1 / 36 = 2 / 72, 1 / 24 = 3 / 72, and 1 / 18 = 4 / 72.Step 6: Sum = 2 / 72 + 3 / 72 + 4 / 72 = 9 / 72 = 1 / 8.Step 7: Therefore 2(a + b + c) = 1 / 8, giving a + b + c = 1 / 16.Step 8: Thus the combined daily rate of A, B and C together is 1 / 16 of the work per day.Step 9: Time taken when A, B and C work together = 1 divided by 1 / 16 = 16 days.
Verification / Alternative check:
We can quickly verify the arithmetic using another denominator like 360 to ensure the fraction sum is correct. Using 360, 1 / 36 = 10 / 360, 1 / 24 = 15 / 360, 1 / 18 = 20 / 360. Their sum is 45 / 360 = 1 / 8, which matches our earlier calculation. Therefore a + b + c = 1 / 16 is reliable, and 16 days is the correct combined time.
Why Other Options Are Wrong:
Common Pitfalls:
Students may try to average the given times instead of working with rates, or they may incorrectly subtract equations, leading to errors in the total rate. Another common issue is adding fractions carelessly without a correct common denominator. Always use rates, not times, and handle fractions with care to avoid arithmetic mistakes.
Final Answer:
All three working together will finish the work in 16 days.
Discussion & Comments